Raviza is one of the renewable hydrogen projects we are developing in Extremadura. We combine solar photovoltaic generation, battery storage and electrolysis to produce renewable hydrogen efficiently and competitively.

Badajoz, Extremadura (Spain)

Raviza in figures

210MW

Electrolysis capacity

622MWp

Peak capacity of the
solar photovoltaic plant

2,000MWh

Battery energy storage capacity (BESS)

15MW

Grid connection

Pressurized alkaline

Electrolysis technology

≈ 20,000 tonnes/year

Estimated RFNBO hydrogen production

Production will be injected into the future hydrogen backbone network being developed by Enagás, allowing the molecule to be transported to national and European consumers and contributing to the decarbonization of industry and transport.

The project

Raviza integrates solar photovoltaic generation, battery energy storage and renewable hydrogen production through pressurized alkaline electrolysis.

  • The photovoltaic plant is made up of 894,930 bifacial modules of 695 Wp, with a peak capacity of 622 MWp.

  • Photovoltaic generation is complemented by a 2,000 MWh battery energy storage system and a 15 MW connection to the electricity grid.

  • The electrolysis production plant has 42 pressurized alkaline electrolyzers of 5 MW, for a total of 210 MW of production.

  • The plant will be connected to the future hydrogen backbone network for the distribution and transport of hydrogen to end consumers.

Location of the Raviza project in the province of Badajoz
Province of Badajoz, Extremadura, Spain

Objectives and impact

  • Approximately 20,000 tonnes of hydrogen per year will be produced for the European hydrogen market, connecting the renewable potential of the Iberian Peninsula with European demand.

  • All of the production will be hydrogen certified as a renewable fuel of non-biological origin (RFNBO), contributing to the decarbonization of sectors that are difficult to electrify, such as industry and heavy transport.

  • Approximately 207,000 tonnes of CO2 will be kept out of the atmosphere thanks to the replacement of fossil fuels with RFNBO hydrogen.

Project timeline

  1. Ready to Build (RtB)

    Estimated start Q3 2029

  2. Commercial Operation Date (COD)

    Estimated start Q1 2032

The main milestones and the timeline will be updated in line with the progress of the project.

Project developer

Raviza is a project developed by Raviza FVH2, S.L., a project company subsidiary of DH2 energy.

Contact

To request further information or documentation about the Raviza project:

Beatriz Maestro Cuartero
Beatriz Maestro CuarteroRenewable Hydrogen Project Managerbmaestro@dh2energy.com
Montse Mancebo de Figarolas
Montse Mancebo de FigarolasFinance Managermmancebo@dh2energy.com

Last updated: October 2026

Back to projects